The California State Auditor, acting at the direction of the Joint Legislative Audit Committee, recently conducted an audit of Riverside Unified School District's Measure O bond expenditures. RUSD welcomes independent oversight; it reflects the accountability our community deserves and the transparency we are committed to upholding.

This page provides supporting resources, including a district-wide investment summary, our press release in response to the audit, links to the full audit report, the original bond documents, and answers to frequently asked questions. For general background on Measure O, visit the Measure O program page.

June 9, 2026 Press Release

RIVERSIDE, Calif., June 9, 2026 — Riverside Unified School District (RUSD) has once again been affirmed in its responsible stewardship of Measure O local bond funds, according to a State audit released today. The audit confirmed that the District's process for selecting Measure O projects complied with applicable laws and requirements, and that expenditures align with the ballot language approved by nearly 70% of Riverside voters in 2016. This finding is consistent with two prior court rulings in the District's favor following legal challenges brought by Riversiders Against Increased Taxes (RAIT).
Read the entire press release here.

Measure O Spending as of June 2026

Measure O: Investing in Riverside Schools

Measure O — Approved by 70% of Riverside Voters, November 2016

Measure O authorized $392 million in bonds to repair, upgrade, and build Riverside schools. Here is what that investment has meant for students across the District.

Filter by construction era:
Pre-Pandemic — completed before cost increases
During Pandemic — navigated inflation
Post-Pandemic — navigated inflation
Under Construction — ongoing investment
Completed & Active Measure O Projects
Pre-Pandemic
Middle School

Sierra Middle School

Feb 2018 – Nov 2019 $9.98M
  • Modernized multi-purpose room, gym, kitchen & library
  • New HVAC, fire alarm & lighting throughout
  • Expanded parking & new student drop-off zone
  • ADA accessibility improvements
Pre-Pandemic
Elementary School

Harrison Elementary

Jul 2019 – Apr 2021 $12.37M
  • New classroom building with 5 classrooms incl. 2 special education
  • 35,000 sq ft new parking & drop-off area
  • New HVAC system
  • Modernized admin office & kindergarten area
Pre-Pandemic
Elementary School

Highgrove Elementary

Jun 2019 – Aug 2020 $24.54M
  • New two-story kindergarten building with 12 classrooms
  • Full campus modernization: HVAC, roof, lighting, fire alarm
  • New playground equipment & kinder play area
  • ADA accessibility upgrades throughout
Pre-Pandemic
Elementary School

Jefferson Elementary

Jun 2019 – Apr 2021 $18.41M
  • New 6-classroom kindergarten building
  • Removed 6 portables; full campus modernization
  • All restrooms upgraded to ADA standards
  • New drainage, gas lines & site utilities
Pre-Pandemic
Elementary School

Madison Elementary

Jun 2019 – Jun 2021 $18.63M
  • New 5-classroom kindergarten wing
  • Removed 5 portables
  • New lunch shelter, bus drop-off & expanded parking
  • Field, landscape & hardscape upgrades
During Pandemic
High School

Arlington High School

Dec 2020 – May 2022 $26.61M
  • New auxiliary gym for practice, assemblies & flex use
  • Stadium expansion: new bleachers, lights, press box & ticket booth
  • New science classrooms & CTE broadcast/graphic arts classroom
  • Special education classrooms & life skills room
  • Renovated pool & pool deck
During Pandemic
Elementary School

John Adams Elementary

Jun 2020 – Nov 2021 $13.99M
  • New 8,737 sq ft kindergarten building with 5 classrooms
  • 3 new play structures with safety surfacing
  • New parking, drop-off area & ornamental fencing
  • Updated utilities: water, sewer, gas & electrical
During Pandemic
Elementary School

Andrew Jackson Elementary

Jun 2020 – Mar 2022 $22.12M
  • New 2-story building with 8 classrooms; removed 8 portables
  • Renovated kindergarten classrooms & new play area
  • Full library, roofing, HVAC & fire alarm modernization
  • New Head Start classroom, lunch shade structure & fencing
During Pandemic
Elementary School

Magnolia Elementary

Jun 2020 – Nov 2021 $12.62M
  • Two new classroom buildings with 10 permanent classrooms
  • New kindergarten playground area
  • New parent drop-off area
  • Site drainage improvements
During Pandemic
High School

Riverside Polytechnic HS

May 2020 – May 2022 $24.04M
  • Entire quad rebuilt to ADA accessibility standards
  • New auxiliary gym
  • Shade canopies & outdoor collaboration spaces
  • Upgraded site utilities & remodeled student entry
During Pandemic
Early Childhood Center

Sunshine Early Childhood Center

Jun 2020 – Dec 2021 $10.8M
  • New modular therapy building
  • 7 classrooms modernized: HVAC, lighting, fire alarm, flooring
  • New play structure & marquee sign
  • Additional parking
During Pandemic
Elementary School

Fremont Elementary

May 2021 – Sep 2022 $18.67M
  • New 2-story & single-story buildings with 12 classrooms
  • Removed 4 portables; new kinder play yard
  • Roof replacement & admin building reconfiguration
  • New parking lot & full ADA accessibility upgrades
During Pandemic
Elementary School

Alcott Elementary

May 2021 – Aug 2022 $21.59M
  • New two-story building with 10 classrooms
  • Removed 11 portables; new hard court & turf play area
  • Full interior & exterior modernization of existing buildings
  • New landscaping, bio-retention area & fencing
Post-Pandemic
Elementary School

Monroe Elementary

May 2021 – Mar 2023 $23.01M
  • New 5-classroom kindergarten building
  • Full HVAC, plumbing, roof & fire alarm modernization
  • 21 new restroom stalls campus-wide
  • New lunch shelter, parking lot & bus drop-off
Post-Pandemic
Elementary School

Longfellow Elementary

Completed Jul 2024 $24.30M
  • New two-story & single-story modular classroom buildings
  • New administration building & well-defined entry point
  • New parking lot on a formerly car-free site
  • Full interior & exterior modernization of 6 existing buildings
Post-Pandemic
Middle School

University Heights Middle School

Jun 2022 – Dec 2023 $15.5M
  • 7 new classrooms replaced aging portables
  • Modernized 15 classrooms; expanded band room
  • Relocated library for improved campus flow
  • New running track, security fencing & ADA upgrades
Post-Pandemic
New Neighborhood School

Casa Blanca Elementary

Completed Fall 2025 $91.7M
  • Brand new TK–6 school on 9.8 acres in Casa Blanca
  • Capacity for 750 students
  • Full range of TK/K, 1–6 classrooms & special education
  • Outdoor learning spaces, play areas & safe drop-off
Post-Pandemic
High School

John W. North High School

Completed Dec 19, 2025 $61.5M
  • New permanent 8-classroom science building
  • New competitive gymnasium
  • Infrastructure, ADA & campus modernization
  • $50M Measure O + $11.5M ESSER funding
Under Construction
New Neighborhood School

Ofelia Valdez-Yeager Eastside Elementary

In Progress $118.25M
  • Brand new TK–6 campus on 6.5 acres
  • Capacity for 900 students in the Eastside neighborhood
  • Adjacent to Abraham Lincoln High School
  • District has acquired 23 properties for this project

Frequently Asked Questions

"To repair and upgrade Riverside schools, including deteriorating roofs, plumbing and electrical systems, improve student safety, security, and seismic safety, upgrade classrooms, science labs, career-training facilities, computer systems and instructional technology to support student achievement in math, science, engineering and skilled trades, and construct, acquire, repair classrooms, sites, facilities and equipment, shall Riverside Unified School District issue $392 million in bonds at legal rates, with citizen oversight, no money for administrator salaries, all money staying local?"

Click Here to read full Text Ballot Proposition and Resolution